Various front and rear extensions complete with Conservatory and new driveway |
 |
| The bungalow before works start |
'
 |
 |
| The jcb has removed all the top soil down to reduced levels for the new driveway. Thank goodness it's sunny and dry |
Foundations dug out at rear ready for concrete |
 |
 |
| Front bedroom extension with roof carcassing almost complete. Just 3 weeks into the job. Amazing |
Rear extension shell being constructed. This prolonged dry spell is a bonus |
 |
 |
| Front Bedroom extension, shell, complete. The front dormer has now been removed |
Rear extension up to wall plate level. Just 4 weeks into the project |
 |
 |
| Akward bit of roof carcassing which tested the skills of the carpenter. Worked out well |
Rear elevation with roof carcassing completed to rear roofs. Base of Conservatory completed |
 |
| Under construction |
| |
| | Return to list of projects |